GlobalFoundries D-Cub


Project Description

O V E R V I E W

Due to previous performance excellence at the Malta campus, Danforth was selected to be a member of the Cub-D CPD (Collaborative Project Delivery) Team.

A P P R O A C H

Working in collaboration with the design team, Danforth assisted in a fast-track design development of the HVAC Piping & Ductwork, Process Ductwork and Plumbing systems for the D-Cub project. The D-Cub will be a 100,000 ft mechanical support building providing facility utility requirements of the TDC building.

R E S U L T S

The CPD Team successfully set new standards for speed to delivery of Issued for Construction (IFC) documents, which were accompanied by a clash-free model, providing the opportunity to move immediately into fabrication and construction. This form of project delivery gave the owner an opportunity for a 4-month schedule gain.